Princeton Sent Back Plans For A McDonald's, 7-Eleven And QT Car Wash. Here's What's Holding Them Up.
Princeton P&Z denied plats for a 7-Eleven and McDonald's, a QT car wash, Shoppes at Monticello and a U.S. 380 restaurant over incomplete engineering. Here's why.
Four commercial projects in some of Princeton's busiest areas, including a 7-Eleven and a McDonald's in Princeton Business Park and a QuikTrip car wash on U.S. 380, were turned back by the city's Planning and Zoning Commission on Nov. 2. Commissioners didn't object to the businesses themselves. They said the developers' paperwork wasn't finished.
"We want the commercial. We need the commercial. We just need it done properly," one commissioner said as the commission wrapped up the plats.
The commission denied all four plats. A plat is the legal map that divides land into lots and has to be approved before a property can be developed. Staff said each had unresolved engineering, traffic or drainage items. In the same meeting, a residential subdivision whose builder had followed the city's checklist was approved without any trouble.
A 30-day clock forces a vote
Part of the reason incomplete plats reach the commission at all is state law. Texas Local Government Code Section 212.009 requires a city to approve, approve with conditions, or disapprove a plat within 30 days after it is filed. Staff called this the "shot clock." Once the city accepts an application, the clock starts, even if a full review later turns up missing pieces. One commissioner asked whether the city could simply send an incomplete plat back for more work. Staff said it can't. Once an application is accepted, the commission has to act on it. Staff also said they can't deny a final plat themselves, so plats with open comments go to the commission for a decision.
Staff said they prefer a clear decision over a rushed review. Plats go through the city's third-party engineering consultant, and staff said trying to clear dozens of comments in a few days is how mistakes happen. "This is going to stay with the land once approved," a staff member told the commission. Staff said that if a final plat is approved while items are still outstanding, the developer can record it with the county, and the city doesn't "get another bite of the apple."
QuikTrip's car wash on U.S. 380
The first denial was a replat by Retail Partners - Princeton LLC for 1.708 acres at the northwest corner of Monte Carlo Boulevard and U.S. 380. The replat would combine two lots into one. A real estate project manager for QuikTrip told commissioners the site is planned for a QT Bubble Bath car wash, an L-shaped parcel that wraps around the existing QuikTrip. He asked for approval with conditions. "We have to address all comments regardless in order to develop the site," he said. He told the commission the company received the city's comments only the week before the meeting.
Commissioners weren't persuaded. One counted roughly 72 open items and said they were major, not minor. Staff confirmed that engineering comments are part of the plat, not a separate step. When the representative asked how a denial would affect the project, a commissioner said it would delay it: instead of going on to City Council, the replat would come back to Planning and Zoning. The commission denied it. A commissioner also noted that the signature on the application didn't match the owner's name, an issue staff had already flagged.
Shoppes at Monticello on FM 75
The commission also denied a final plat by Cope Retail LLC for Shoppes at Monticello, about 4.1 acres split into two lots on the east side of FM 75 between Monticello Drive and East Monte Carlo Boulevard. Staff said the planning comments were fairly minor but several engineering comments were still open, and no revised plat had come in. The city received the plat Oct. 5, so the 30-day deadline was Nov. 5 and the commission had to act at this meeting. No one from the development spoke.
A restaurant at 107 W. Princeton Drive
A preliminary plat by property owner D.L. Caldwell for a restaurant on 1.37 acres at 107 W. Princeton Drive, on the south side of U.S. 380 about 65 feet east of Town Park Avenue, was denied as well. A staff member said they believed it would be a Korean fusion restaurant. Staff said the city's engineers couldn't review it at all because the preliminary engineering was missing. Staff also said the applicant had a pre-application meeting and received the city's checklist, which is posted on the city website and spells out what each type of plat needs. "How do you submit this without even engineering?" one commissioner asked.
The 7-Eleven and McDonald's in Princeton Business Park
The last denial was a replat by JB Princeton I, LP for about 9.4 acres at the northwest corner of Myrick Lane and South Beauchamp Boulevard in Princeton Business Park. The replat would create four commercial lots on land currently zoned for light industrial use. Development Services Director Shai Roos said the lots are for a 7-Eleven and a McDonald's and that the area needs neighborhood retail.
Staff called it a legacy project. The land was platted before the city started requiring preliminary engineering, so the city let the developer do a replat as long as it supplied that engineering. The plat drawing itself had no remaining comments, but the supporting documents did. A traffic impact analysis signed off by the city's engineers requires the developer to build a right-turn deceleration lane, and staff said the city needs to see that design before engineering will recommend approval. Staff said a variance for driveway spacing will also be needed later. Roos said the city had tried to work with the developer's timeline, "which hasn't truly worked." The commission denied the replat.
The subdivision that followed the checklist
The contrast came from a residential plat on the same agenda. The commission voted 6-0 to approve the final plat for KB Home's Princeton Estates Phase 2, about 29.8 acres at County Road 456 and South Boorman Lane. Staff said the builder had followed the checklist, fixed its remaining items before the meeting, and gotten through in about two reviews.
"Hopefully the contractors and the developers and everyone else coming to our city and coming forward to us understand they've got to follow, basically follow a checklist," one commissioner said after the business park vote. "And if you don't have the checklist completed, you shouldn't submit yet."